If you drive an electric car, or plan to, the rules for adding a charger in a strata building change for most of Metro Vancouver at the end of this year. The Province's page on electrical planning reports says every strata corporation with five or more strata lots in the Metro Vancouver Regional District must obtain one by December 31, 2026. Once a strata has its report, or that date passes, a set process in the Strata Property Act decides how the council handles your request for a charger. Below is how that process works, who pays, and what a buyer should check. We read each source on November 4, 2026.
An electrical planning report is a study of the building's electricity supply. The Province lists what it must contain:
- the current capacity of the strata's electrical system,
- a list of what already draws power from it,
- an estimate of peak demand and of the spare capacity left over,
- an estimate of the capacity needed for future demands, such as EV charging and heat pumps, and
- ideas for lowering demand, such as switching common area lights to LED.
The deadline depends on where the building is. Strata corporations in Metro Vancouver, the Fraser Valley and the Capital Regional District must have one by December 31, 2026, apart from islands reached only by air or boat. Everywhere else in BC, the date is December 31, 2028. A new strata has five years from the day its strata plan was deposited.
The strata can pay for the report from the operating fund, if it is in the budget passed at the annual general meeting, or from the contingency reserve fund by a majority vote. The report is a general overview. The Province says it cannot be used to plan a specific installation; a qualified professional still has to confirm the capacity for your charger.
The Province's page on EV charging in stratas sets out the steps, which come from sections 90.1 to 90.3 of the Strata Property Act. The process applies once the strata has its electrical planning report or once the deadline has passed. For a strata with fewer than five lots, it applies from December 31, 2026.
Your written request must include:
- your contact details and strata lot number,
- a description of the charger or other charging equipment,
- the place where it would be used, such as your parking stall,
- the name and contact details of a qualified contractor,
- the contractor's description of the work needed, and
- the contractor's estimate of the cost and the time to finish.
Get the contractor's quote before you write to the council. A request missing one of these items is incomplete, and the protections below apply to a request made properly under section 90.1.
The council must decide within 3 months of receiving the request. It cannot unreasonably refuse a properly made request. The Province gives one example of a valid reason to refuse: the building does not have enough electrical capacity to support it. The council may weigh the capacity of the system and the current and expected demands on it, which is where the electrical planning report helps.
If the council approves, it may ask you to agree in writing to reasonable conditions. The Province lists examples: the strata approves the equipment, the contractor and the materials; you pay the installation cost in advance; and you agree to change or replace your equipment later if the strata installs a shared charging system for more owners. The council can let you do the work or have the strata do it.
For a single owner's charger, expect to pay. The Province says the strata council can require the owner to pay the costs of installation.
A strata can also decide to add charging for many owners at once. Since May 11, 2023, several of those decisions need only a majority vote instead of a 3/4 vote, according to the Province's summary of law changes:
- spending from the contingency reserve fund on charging equipment, on managing the power it uses, or on a report about it (section 96),
- a "significant change in use or appearance" of common property for charging (section 71), and
- buying or selling charging stations owned by the strata (section 82).
A special levy for charging still needs a 3/4 vote. Our post on strata fees explains the contingency reserve fund and special levies.
The Province's page on parking stalls and storage lockers says the strata plan shows how each stall is held: as part of a strata lot, as limited common property for one strata lot's use, or as common property. One way a strata assigns a common property stall is a short-term exclusive use privilege, which may not run longer than one year. A charger changes that limit. The Province says a strata can give an owner exclusive use of a common property stall for up to 5 years, if a charger is installed in that stall after the owner's request under section 90.1 and the owner paid for the installation. The Form B must also disclose how parking stalls and storage lockers are allocated.
A strata can recover the cost of power used for charging through a user fee. Under Strata Property Regulation 6.9, the fee can be a rate based on use, but it must be reasonable and set out in a bylaw or in a rule that owners have ratified by majority vote at a general meeting.
A strata with five or more attached units that supplies power to chargers may be able to earn and sell low carbon fuel credits under BC's Low Carbon Fuels Act. The Province lists three tests: charging happens at a building with five or more attached homes, the strata supplies and pays for the electricity to the chargers, and the electricity can be measured. A strata that chooses to report its charging would sell the credits through an allocator, at a price the market sets.
If you plan to charge a car at home, add these items to your review of the building before your subjects come off:
- The electrical planning report, once the strata has it. It is a permanent record and must be disclosed on the Form B Information Certificate when a buyer requests one.
- Any EV Ready Plan. The Province describes it as a separate plan that sets out what is needed to put charging in every stall.
- Council and general meeting minutes from the last 2 years, for owner requests, refusals and votes on charging.
- The bylaws and rules, for an electricity user fee.
- The parking stall: whether it is part of the strata lot, limited common property or common property, and which stall the Form B allocates to the unit.
For an owner, there is one step to take this month. Ask your property manager whether the electrical planning report has been ordered, and when the council expects it. If you want a charger, start collecting a contractor's quote now so your request is complete when the process applies.
If you are comparing buildings downtown and charging matters to you, call us at 604-992-8612 or send a note through our contact form. Our team will be in touch within 24 hours.